100kw CMPS Pty Ltd system

When taking on a system of this magnitude there is a lot of planning and negotiating with local utility’s, engineers, designers and of course the client, also with recent changes in the Australian standards there were many issues to consider.

Working together with BTS Energy we were given the task of putting 400 panels on an east and west facing aspect and due to engineering confinements weren’t able tilt the system, the roof had a 10 degree pitch and when facing the panels to the East or West you lose about 13% efficiency but the size of the system more than compensated for the loss.

After months of planning , 4 weeks on the job and a lot of very hot summer days on the roof the job was complete and is now producing on average over 400kw/hrs a day putting a major dent in CMPS’s energy bill and is looking to pay itself off in about 5 years.